| custom text fields |
| I know that Project 2007 can handle a text field (#1-30) of up to 255
characters but when I go to add that field to the Task Sheet, it
limits me to 128 characters. Any clues? I really need the whol... on 20-Nov-09 |
| |
|
| Baseline - Entered or Calcuated rollups |
| I???m having a problem/ question with the baseline rollup option because we
have come across a situation where the Baseline Work on the summary task did
not rollup as expected.
1) How come when we m... on 20-Nov-09 |
| |
|
| Task start/end dates from MS project to Workspace site |
| We are currently running MSPS 2007 with WSS 3.0. I am trying to create a list in one of the project work spaces. I would like to auto-populate two columns in that list with the start and end date of ... on 20-Nov-09 |
| |
|
| My Task actual hour |
| I am having an issue in the Project Plan where actual hour that were
imported from the timesheet into My Task page and approved by the project
manager does not appear in the project plan. Any sugges... on 20-Nov-09 |
| |
|
| Projects checked-out "automatically"!?! |
| Hi there!
We've several issues with projects that are checked-out "anyhow"...
Our setting is MS Project Server 2007, SP2, April CUP. August CUP not in use
due to several issues that we have experie... on 20-Nov-09 |
| |
|
|
|
| Project server 2007 deleted user by mistake |
| Hi,
We are using project server 2007 forms authentication. By mistake I
deleted one user from the project web access --> server setting -->delete
enterprise objects objects. But the timesheet for the... on 19-Nov-09 |
| |
|
|
|