You can change the reporting units in the timesheet from hours to days and |
pconroyATtheprojectserverguruDOTcoDOTnz posted on Saturday, May 24, 2008 5:04 PM
|
You can change the reporting units in the timesheet from hours to days and
then import the timesheet data into task updates
server settings>Timesheet Settings & Defaults>Default Reporting Units
With the tracking method set to "Actual work done and work remaining", you
are presented with work planned in days and the amount of effort spent can be
entered in days. However you don't get a timephased entry table as you do
when reporting using "Hours of work done per period"
--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/
http://theprojectserverguru.spaces.live.com |
 |
|
Thank you Paul, appreciating your helpExecutives want to see "Days" instead of |
LemonWithMin posted on Sunday, May 25, 2008 3:40 AM
|
Thank you Paul, appreciating your help
Executives want to see "Days" instead of "Hours" in the Work field for all
the available views.
I tried your suggestion but still "Hours" appear in the Work field. are you
sure this will address our requirement here?
Thank you, |
 |
|
No it won't. |
pconroyATtheprojectserverguruDOTcoDOTnz posted on Sunday, May 25, 2008 5:36 AM
|
No it won't.
You could however create a custom field to recalculate work to days and show
this column instead of the work column.
Paul
--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/
http://theprojectserverguru.spaces.live.com |
 |
|
Thank you again PaulYou are right; this might be a possible workaround. |
LemonWithMin posted on Sunday, May 25, 2008 8:50 AM
|
Thank you again Paul
You are right; this might be a possible workaround. Do you know other
alternatives? |
 |
|
sorry no.-- Did this post help you. |
pconroyATtheprojectserverguruDOTcoDOTnz posted on Sunday, May 25, 2008 2:02 PM
|
sorry no.
--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/
http://theprojectserverguru.spaces.live.com |
 |
|